Showing posts with label Software Project Management. Show all posts
Showing posts with label Software Project Management. Show all posts

Friday, June 5, 2009

Software Project Management Exam Tips





Exam date: Saturday 13th June 2009

These should be the most important sections to read:

    Topics

  1. NPV, ROI, payback
  2. WBS, Weighted scoring model
  3. For WBS must at least three levels
  4. Check example of building a house
  5. EVM
  6. Textbook pp 285-291
  7. Tutorial 12 (Chapter7revised) page1 q1
  8. AOA
  9. Tutorial 8 page 2
  10. Text book pp 223-224, 255(q2)
  11. Project time management
  12. Critical path is the longest path


EVM Formulas

  1. EV = PV to date * RP
  2. CV = EV - AC
  3. SV = EV - PV
  4. CPI = EV/AC
  5. SPI = EV/PV
  6. EAC = BAC/CPI
  7. ETC= OTE/SPI

EV - Earned Value

PV - Planned Value

RP - Rate of Performance

CV- Cost Variance

AC- Actual cost

SV- Schedule Variance

CPI- Cost Performance Index

SPI- Schedule Performance Index

EAC- Estimate at Completion

BAC-Budget at Completion

ETC-Estimated Time to Complete

OTE-Original Time Estimate


Analyzing

Important factors in project are cost and time

  • CV represents the cost performance
  • SV represents the time performance
  • If they are positive, they are ahead of schedule/under budget if negative they are behind schedule/ over budget
  • CPI represents the cost performance as an index/performance. It verifies the CV
  • SPI represents the time performance as an index/performance. It verifies the SV
  • Over 100% is good ( they are ahead of schedule/under budget ) 100% is neutral and below 100% is bad (behind schedule/ over budget)
  • If EAC is higher than BAC then the project is performing worse than planned because the new estimate to complete the project is x more than planned.
  • You get OTE from the question, where they mention how long the project was intended to take
  • If ETC is higher than OTE then the project is performing worse than planned because the project is projected to take x months longer than planned.
GOOOOOOOOOOOOOOOD LUCK!!

Thursday, June 4, 2009

Some tips on SPM

1. Cauculate the NPV ROI etc.........
2. focus on chapter 5-6-7...
3. Calculate the earned value management (EVM) text book page: 285

This first, any aditional tips will be availabe soon :D